Roadway Improvement Program / Road Reconstruction (3R/4R Standards) at County Line Rd (1382598)
VERSION
SFY
SOURCE
PE
ROW
CON
CE
TOTAL
11
22-51 2022 May Admin Mod
2022
STBG Chicago UZA
$0
$252,800
$0
$0
$252,800
11
22-51 2022 May Admin Mod
2022
Local Fund
$0
$63,200
$0
$0
$63,200
11
22-51 2022 May Admin Mod
2027
Local Fund
$0
$0
$8,596,250
$0
$8,596,250
TOTAL FOR VERSION 11
$0
$316,000
$8,596,250
$0
$8,912,250
10
22-15 2021 Admin Mod to add total costs to project missing phases.
2016
Local Fund
$860,000
$0
$0
$0
$860,000
10
22-15 2021 Admin Mod to add total costs to project missing phases.
2022
STBG Chicago UZA
$0
$252,800
$0
$0
$252,800
10
22-15 2021 Admin Mod to add total costs to project missing phases.
2022
Local Fund
$0
$63,200
$0
$0
$63,200
10
22-15 2021 Admin Mod to add total costs to project missing phases.
2027
STBG Chicago UZA
$0
$0
$6,877,000
$0
$6,877,000
10
22-15 2021 Admin Mod to add total costs to project missing phases.
2027
Local Fund
$0
$0
$1,719,250
$0
$1,719,250
TOTAL FOR VERSION 10
$860,000
$316,000
$8,596,250
$0
$9,772,250
8
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2022
STBG Chicago UZA
$0
$252,800
$0
$0
$252,800
8
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2022
Local Fund
$0
$63,200
$0
$0
$63,200
8
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2027
STBG Chicago UZA
$0
$0
$6,877,000
$0
$6,877,000
8
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2027
Local Fund
$0
$0
$1,719,250
$0
$1,719,250
TOTAL FOR VERSION 8
$0
$316,000
$8,596,250
$0
$8,912,250
7
20-11.3 2021 TIP correction December 2020
2022
STBG Chicago UZA
$0
$252,800
$0
$0
$252,800
7
20-11.3 2021 TIP correction December 2020
2022
Local Fund
$0
$63,200
$0
$0
$63,200
7
20-11.3 2021 TIP correction December 2020
2027
STBG Chicago UZA
$0
$0
$6,877,000
$0
$6,877,000
7
20-11.3 2021 TIP correction December 2020
2027
Local Fund
$0
$0
$1,719,250
$0
$1,719,250
TOTAL FOR VERSION 7
$0
$316,000
$8,596,250
$0
$8,912,250
6
20-06.2 2020 February 2020 Administrative Modification
2021
STBG Chicago UZA
$0
$200,000
$0
$0
$200,000
6
20-06.2 2020 February 2020 Administrative Modification
2021
Local Fund
$0
$50,000
$0
$0
$50,000
6
20-06.2 2020 February 2020 Administrative Modification
2022
STBG Chicago UZA
$0
$0
$6,877,000
$0
$6,877,000
6
20-06.2 2020 February 2020 Administrative Modification
2022
Local Fund
$0
$0
$1,719,250
$0
$1,719,250
TOTAL FOR VERSION 6
$0
$250,000
$8,596,250
$0
$8,846,250
5
20-06.1 2020 January 2020 Administrative Modification
2020
STBG Chicago UZA
$0
$200,000
$0
$0
$200,000
5
20-06.1 2020 January 2020 Administrative Modification
2020
Local Fund
$0
$50,000
$0
$0
$50,000
5
20-06.1 2020 January 2020 Administrative Modification
2022
STBG Chicago UZA
$0
$0
$6,877,000
$0
$6,877,000
5
20-06.1 2020 January 2020 Administrative Modification
2022
Local Fund
$0
$0
$1,719,250
$0
$1,719,250
TOTAL FOR VERSION 5
$0
$250,000
$8,596,250
$0
$8,846,250
4
20-00 2020 NWI 2020-2024 Transportation Improvement Program
2020
STBG Chicago UZA
$0
$200,000
$0
$0
$200,000
4
20-00 2020 NWI 2020-2024 Transportation Improvement Program
2020
Local Fund
$0
$50,000
$0
$0
$50,000
4
20-00 2020 NWI 2020-2024 Transportation Improvement Program
2021
STBG Chicago UZA
$0
$0
$6,877,000
$0
$6,877,000
4
20-00 2020 NWI 2020-2024 Transportation Improvement Program