Roadway Improvement Program / Road Reconstruction (3R/4R Standards) at County Line Rd (1382598)
Des Number 1382598 Amendment 20-11.3 ADMIN MOD Exempt Category Non-Exempt Est Total Project Cost $8,912,250
Lead Agency Hobart Contact (ERC) Gralik, Phillip 2199428271 County Lake
Project Type Roadway Reconstruction/Rehabilitation Letting Date 10/07/2020 Functional Classification Minor Collector Bike/Ped Component(s) Yes 05%
Title Roadway Improvement Program / Road Reconstruction (3R/4R Standards) at County Line Rd
Limits From US 6 to Cleveland Ave of Distance (mile) 1
Description from US 6 to Cleveland Ave
Phase Fund Source Prior SFY SFY2020 SFY2021 SFY2022 SFY2023 SFY2024 Future SFY Total
RW Local Fund - - - $63,200 - - - $63,200
RW STBG Chicago UZA - - - $252,800 - - - $252,800
Total Right of Way - - - $316,000 - - - $316,000
CN Local Fund - - - - - - $1,719,250 $1,719,250
CN STBG Chicago UZA - - - - - - $6,877,000 $6,877,000
Total Construction - - - - - - $8,596,250 $8,596,250
Total Programmed - - - $316,000 - - $8,596,250 $8,912,250
Map Coming Soon

Map location not available

<< Go Back
Roadway Improvement Program / Road Reconstruction (3R/4R Standards) at County Line Rd (1382598)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  8   22-00 2022 2022-2026 TIP adoption   2022   STBG Chicago UZA   $0   $252,800   $0   $0   $252,800  
  8   22-00 2022 2022-2026 TIP adoption   2022   Local Fund   $0   $63,200   $0   $0   $63,200  
  8   22-00 2022 2022-2026 TIP adoption   2027   STBG Chicago UZA   $0   $0   $6,877,000   $0   $6,877,000  
  8   22-00 2022 2022-2026 TIP adoption   2027   Local Fund   $0   $0   $1,719,250   $0   $1,719,250  
TOTAL FOR VERSION 8 $0   $316,000   $8,596,250   $0   $8,912,250  
  7   20-11.3 2021 TIP correction December 2020   2022   STBG Chicago UZA   $0   $252,800   $0   $0   $252,800  
  7   20-11.3 2021 TIP correction December 2020   2022   Local Fund   $0   $63,200   $0   $0   $63,200  
  7   20-11.3 2021 TIP correction December 2020   2027   STBG Chicago UZA   $0   $0   $6,877,000   $0   $6,877,000  
  7   20-11.3 2021 TIP correction December 2020   2027   Local Fund   $0   $0   $1,719,250   $0   $1,719,250  
TOTAL FOR VERSION 7 $0   $316,000   $8,596,250   $0   $8,912,250  
  6   20-06.2 2020 February 2020 Administrative Modification   2021   STBG Chicago UZA   $0   $200,000   $0   $0   $200,000  
  6   20-06.2 2020 February 2020 Administrative Modification   2021   Local Fund   $0   $50,000   $0   $0   $50,000  
  6   20-06.2 2020 February 2020 Administrative Modification   2022   STBG Chicago UZA   $0   $0   $6,877,000   $0   $6,877,000  
  6   20-06.2 2020 February 2020 Administrative Modification   2022   Local Fund   $0   $0   $1,719,250   $0   $1,719,250  
TOTAL FOR VERSION 6 $0   $250,000   $8,596,250   $0   $8,846,250  
  5   20-06.1 2020 January 2020 Administrative Modification   2020   STBG Chicago UZA   $0   $200,000   $0   $0   $200,000  
  5   20-06.1 2020 January 2020 Administrative Modification   2020   Local Fund   $0   $50,000   $0   $0   $50,000  
  5   20-06.1 2020 January 2020 Administrative Modification   2022   STBG Chicago UZA   $0   $0   $6,877,000   $0   $6,877,000  
  5   20-06.1 2020 January 2020 Administrative Modification   2022   Local Fund   $0   $0   $1,719,250   $0   $1,719,250  
TOTAL FOR VERSION 5 $0   $250,000   $8,596,250   $0   $8,846,250  
  4   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2020   STBG Chicago UZA   $0   $200,000   $0   $0   $200,000  
  4   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2020   Local Fund   $0   $50,000   $0   $0   $50,000  
  4   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2021   STBG Chicago UZA   $0   $0   $6,877,000   $0   $6,877,000  
  4   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2021   Local Fund   $0   $0   $1,719,250   $0   $1,719,250  
TOTAL FOR VERSION 4 $0   $250,000   $8,596,250   $0   $8,846,250  
  3   18-21 2019 July 2019 Admin Mod   2020   STBG Chicago UZA   $0   $200,000   $0   $0   $200,000  
  3   18-21 2019 July 2019 Admin Mod   2020   Local Fund   $0   $50,000   $0   $0   $50,000  
  3   18-21 2019 July 2019 Admin Mod   2022   STBG Chicago UZA   $0   $0   $6,877,000   $0   $6,877,000  
  3   18-21 2019 July 2019 Admin Mod   2022   Local Fund   $0   $0   $1,719,250   $0   $1,719,250  
TOTAL FOR VERSION 3 $0   $250,000   $8,596,250   $0   $8,846,250  
  2   18-12 2019 December 2018   2020   STBG Chicago UZA   $0   $200,000   $0   $0   $200,000  
  2   18-12 2019 December 2018   2020   Local Fund   $0   $50,000   $0   $0   $50,000  
  2   18-12 2019 December 2018   2021   STBG Chicago UZA   $0   $0   $6,877,000   $0   $6,877,000  
  2   18-12 2019 December 2018   2021   Local Fund   $0   $0   $1,719,250   $0   $1,719,250  
TOTAL FOR VERSION 2 $0   $250,000   $8,596,250   $0   $8,846,250  
  1   18-00 2018    2020   STBG Chicago UZA   $0   $200,000   $0   $0   $200,000  
  1   18-00 2018    2020   Local Fund   $0   $50,000   $0   $0   $50,000  
  1   18-00 2018    2021   STBG Chicago UZA   $0   $0   $6,877,000   $0   $6,877,000  
  1   18-00 2018    2021   Local Fund   $0   $0   $1,719,250   $0   $1,719,250  
TOTAL FOR VERSION 1 $0   $250,000   $8,596,250   $0   $8,846,250  
<< Go Back
Roadway Improvement Program / Road Reconstruction (3R/4R Standards) at County Line Rd (1382598)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  8     22-00 2022-2026 2022 TIP    ROADWAY IMPROVEMENT PROGRAM / ROAD RECONSTRUCTION (3R/4R STANDARDS) AT COUNTY LINE RD   PROGRAMMED     
  7     20-11.3 2021 ADMIN   ROADWAY IMPROVEMENT PROGRAM / ROAD RECONSTRUCTION (3R/4R STANDARDS) AT COUNTY LINE RD   PROGRAMMED   N/A  
  6     20-06.2 February 2020 ADMIN   ROADWAY IMPROVEMENT PROGRAM / ROAD RECONSTRUCTION (3R/4R STANDARDS) AT COUNTY LINE RD   PROGRAMMED   N/A  
  5     20-06.1 January 2020 ADMIN   ROADWAY IMPROVEMENT PROGRAM / ROAD RECONSTRUCTION (3R/4R STANDARDS) AT COUNTY LINE RD   PROGRAMMED   N/A  
  4     20-00 2020 TIP    ROADWAY IMPROVEMENT PROGRAM / ROAD RECONSTRUCTION (3R/4R STANDARDS) AT COUNTY LINE RD   PROGRAMMED   8/22/19  
  3     18-21 2019 ADMIN   ROAD RECONSTRUCTION (3R/4R STANDARDS) AT COUNTY LINE RD   PROGRAMMED   N/A  
  2     18-12 Q2 2019 ADMIN   ROAD RECONSTRUCTION (3R/4R STANDARDS) AT COUNTY LINE RD   PROGRAMMED   N/A  
  1     18-00 Q4 2018 TIP    ROAD RECONSTRUCTION (3R/4R STANDARDS) AT COUNTY LINE RD   PROGRAMMED   8/17/18