Bridge Deck Overlay at I 80 (1500674)
Des Number 1500674 Amendment 22-54 ADMIN MOD Exempt Category Non-Exempt Est Total Project Cost $11,422,052
Contract # Contact (ERC) Julie Ritzler 2193257497 County Lake
Lead Agency INDOT Letting Date 07/08/2020 Functional Classification Interstate Bike/Ped Component(s) No
Project Type Bridge Deck Overlay
Title Bridge Deck Overlay at I 80
Limits Bridge #: 45625
Description I-80 WB Ramp NS RR and EJ&E RR, 0.50mi E of SR 912
Phase Fund Source Prior SFY SFY2022 SFY2023 SFY2024 SFY2025 SFY2026 Future SFY Total
PE NHPP Interstate - - $82,000 - - - - $82,000
PE State Special Projects $75,000 - - - - - - $75,000
Total Preliminary Engineering $75,000 - $82,000 - - - - $157,000
RW State Special Projects - $30,000 - - - - - $30,000
Total Right of Way - $30,000 - - - - - $30,000
CN NHPP Interstate - - $11,235,052 - - - - $11,235,052
Total Construction - - $11,235,052 - - - - $11,235,052
Total Programmed $75,000 $30,000 $11,317,052 - - - - $11,422,052
Map Coming Soon

Map location not available

<< Go Back
Bridge Deck Overlay at I 80 (1500674)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  5   22-54 2022 correction of funds in INDOT projects.   2020   State Special Projects   $75,000   $0   $0   $0   $75,000  
  5   22-54 2022 correction of funds in INDOT projects.   2022   State Special Projects   $0   $30,000   $0   $0   $30,000  
  5   22-54 2022 correction of funds in INDOT projects.   2023   NHPP Interstate   $82,000   $0   $11,235,052   $0   $11,317,052  
TOTAL FOR VERSION 5 $157,000   $30,000   $11,235,052   $0   $11,422,052  
  4   22-51 2022 May Admin Mod   2020   State Special Projects   $75,000   $0   $0   $0   $75,000  
  4   22-51 2022 May Admin Mod   2023   NHPP Interstate   $157,000   $0   $11,235,052   $0   $11,392,052  
TOTAL FOR VERSION 4 $232,000   $0   $11,235,052   $0   $11,467,052  
  3   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2020   State Special Projects   $75,000   $0   $0   $0   $75,000  
  3   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   State Special Projects   $157,000   $0   $11,235,052   $0   $11,392,052  
TOTAL FOR VERSION 3 $232,000   $0   $11,235,052   $0   $11,467,052  
  2   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2020   NHPP Interstate   $67,500   $0   $0   $0   $67,500  
  2   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2020   State Match   $7,500   $0   $0   $0   $7,500  
  2   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2021   NHPP Interstate   $141,300   $0   $1,794,038   $0   $1,935,338  
  2   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2021   State Match   $15,700   $0   $199,338   $0   $215,038  
TOTAL FOR VERSION 2 $232,000   $0   $1,993,376   $0   $2,225,376  
  1   18-00 2018    2020   NHPP Interstate   $67,500   $0   $0   $0   $67,500  
  1   18-00 2018    2020   State Match   $7,500   $0   $0   $0   $7,500  
  1   18-00 2018    2021   NHPP Interstate   $141,300   $0   $1,794,038   $0   $1,935,338  
  1   18-00 2018    2021   State Match   $15,700   $0   $199,338   $0   $215,038  
TOTAL FOR VERSION 1 $232,000   $0   $1,993,376   $0   $2,225,376  
<< Go Back
Bridge Deck Overlay at I 80 (1500674)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  5     22-54 August 2022 ADMIN   BRIDGE DECK OVERLAY AT I 80   PROGRAMMED   N/A  
  4     22-51 July 2022 ADMIN   BRIDGE DECK OVERLAY AT I 80   PROGRAMMED   N/A  
  3     22-00 2022-2026 2022 TIP    BRIDGE DECK OVERLAY AT I 80   PROGRAMMED   06/17/2022  
  2     20-00 2020 TIP    BRIDGE DECK OVERLAY AT I 80   PROGRAMMED   8/22/19  
  1     18-00 Q4 2018 TIP    BRIDGE DECK OVERLAY AT I 80   PROGRAMMED   8/17/18