Intersection Improvement with added Turn Lanes (1702995)
Des Number 1702995 Amendment 22-00 STIP Exempt Category Exempt Est Total Project Cost $7,756,393
Lead Agency INDOT Contact (ERC) Julie Ritzler 2193257497 County Porter
Project Type Intersect. Improv. W/ Added Turn Lanes Letting Date Functional Classification Other Freeway/Expressway Bike/Ped Component(s) No
Title Intersection Improvement with added Turn Lanes
Limits Nearest Crossstreet: Gateway Blvd
Description SR 49 @ I 80/90 (toll road) ramp intersection with Gateway Blvd, located within the town of Chesterton. There are two des numbers on this contract. This is the lead des.
Phase Fund Source Prior SFY SFY2022 SFY2023 SFY2024 SFY2025 SFY2026 Future SFY Total
PE NHPP Non Interstate $168,000 - - - - - - $168,000
PE State Match $42,000 - - - - - - $42,000
Total Preliminary Engineering $210,000 - - - - - - $210,000
RW State Special Projects - - $100,000 - - - - $100,000
Total Right of Way - - $100,000 - - - - $100,000
CN State Special Projects - $150,000 $7,296,393 - - - - $7,446,393
Total Construction - $150,000 $7,296,393 - - - - $7,446,393
Total Programmed $210,000 $150,000 $7,396,393 - - - - $7,756,393
Map Coming Soon

Map location not available

<< Go Back
Intersection Improvement with added Turn Lanes (1702995)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  3   22-00 2022 2022-2026 TIP adoption   2020   NHPP Non Interstate   $168,000   $0   $0   $0   $168,000  
  3   22-00 2022 2022-2026 TIP adoption   2020   State Match   $42,000   $0   $0   $0   $42,000  
  3   22-00 2022 2022-2026 TIP adoption   2022   State Special Projects   $0   $0   $150,000   $0   $150,000  
  3   22-00 2022 2022-2026 TIP adoption   2023   State Special Projects   $0   $100,000   $7,296,393   $0   $7,396,393  
TOTAL FOR VERSION 3 $210,000   $100,000   $7,446,393   $0   $7,756,393  
  2   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2020   NHPP Non Interstate   $168,000   $0   $0   $0   $168,000  
  2   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2020   State Match   $42,000   $0   $0   $0   $42,000  
  2   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2022   NHPP Non Interstate   $56,000   $0   $0   $0   $56,000  
  2   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2022   State Match   $14,000   $0   $467,880   $0   $481,880  
  2   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2023   NHPP Non Interstate   $0   $0   $1,871,518   $0   $1,871,518  
TOTAL FOR VERSION 2 $280,000   $0   $2,339,398   $0   $2,619,398  
  1   18-08 2018 Res 18-13; Amend 16 (Aug); STIP 18-30   2020   NHPP Non Interstate   $168,000   $0   $0   $0   $168,000  
  1   18-08 2018 Res 18-13; Amend 16 (Aug); STIP 18-30   2020   State Match   $42,000   $0   $0   $0   $42,000  
  1   18-08 2018 Res 18-13; Amend 16 (Aug); STIP 18-30   2022   NHPP Non Interstate   $56,000   $0   $0   $0   $56,000  
  1   18-08 2018 Res 18-13; Amend 16 (Aug); STIP 18-30   2022   State Match   $14,000   $0   $467,880   $0   $481,880  
  1   18-08 2018 Res 18-13; Amend 16 (Aug); STIP 18-30   2023   NHPP Non Interstate   $0   $0   $1,871,518   $0   $1,871,518  
TOTAL FOR VERSION 1 $280,000   $0   $2,339,398   $0   $2,619,398  
<< Go Back
Intersection Improvement with added Turn Lanes (1702995)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  3     22-00 2022-2026 2022 TIP    INTERSECTION IMPROVEMENT WITH ADDED TURN LANES   PROGRAMMED     
  2     20-00 2020 TIP    INTERSECTION IMPROVEMENT WITH ADDED TURN LANES   PROGRAMMED   8/22/19  
  1     18-08 Q1 2018 INDOT   INTERSECTION IMPROVEMENT WITH ADDED TURN LANES   PROGRAMMED   10/11/2018