|
<< Go Back
|
|
Bridge Replacement (1703012)
|
|
|
|
Phase |
Fund Source
|
Prior SFY |
SFY2022 |
SFY2023 |
SFY2024 |
SFY2025 |
SFY2026 |
Future SFY |
Total |
PE |
NHPP Non Interstate |
$64,000 |
$16,000
|
-
|
-
|
-
|
-
|
-
|
$80,000 |
PE |
State Match |
$16,000 |
$4,000
|
-
|
-
|
-
|
-
|
-
|
$20,000 |
Total Preliminary Engineering |
$80,000 |
$20,000 |
- |
- |
- |
- |
- |
$100,000 |
CN |
NHPP Non Interstate |
- |
-
|
$901,518
|
-
|
-
|
-
|
-
|
$901,518 |
CN |
State Match |
- |
-
|
$225,380
|
-
|
-
|
-
|
-
|
$225,380 |
Total Construction |
- |
- |
$1,126,898 |
- |
- |
- |
- |
$1,126,898 |
Total Programmed |
$80,000 |
$20,000
|
$1,126,898
|
-
|
-
|
-
|
-
|
$1,226,898 |
|
Map Coming Soon
Map location not available
|
|
<< Go Back
|
|
Bridge Replacement (1703012)
|
VERSION |
SFY |
SOURCE |
PE |
ROW |
CON |
CE |
TOTAL |
3 |
22-00 2022 2022-2026 TIP adoption |
2020 |
NHPP Non Interstate |
$64,000 |
$0 |
$0 |
$0 |
$64,000 |
3 |
22-00 2022 2022-2026 TIP adoption |
2020 |
State Match |
$16,000 |
$0 |
$0 |
$0 |
$16,000 |
3 |
22-00 2022 2022-2026 TIP adoption |
2022 |
NHPP Non Interstate |
$16,000 |
$0 |
$0 |
$0 |
$16,000 |
3 |
22-00 2022 2022-2026 TIP adoption |
2022 |
State Match |
$4,000 |
$0 |
$0 |
$0 |
$4,000 |
3 |
22-00 2022 2022-2026 TIP adoption |
2023 |
NHPP Non Interstate |
$0 |
$0 |
$901,518 |
$0 |
$901,518 |
3 |
22-00 2022 2022-2026 TIP adoption |
2023 |
State Match |
$0 |
$0 |
$225,380 |
$0 |
$225,380 |
|
TOTAL FOR VERSION 3 |
$100,000 |
$0 |
$1,126,898 |
$0 |
$1,226,898 |
|
2 |
20-00 2020 NWI 2020-2024 Transportation Improvement Program |
2020 |
NHPP Non Interstate |
$64,000 |
$0 |
$0 |
$0 |
$64,000 |
2 |
20-00 2020 NWI 2020-2024 Transportation Improvement Program |
2020 |
State Match |
$16,000 |
$0 |
$0 |
$0 |
$16,000 |
2 |
20-00 2020 NWI 2020-2024 Transportation Improvement Program |
2022 |
NHPP Non Interstate |
$16,000 |
$0 |
$0 |
$0 |
$16,000 |
2 |
20-00 2020 NWI 2020-2024 Transportation Improvement Program |
2022 |
State Match |
$4,000 |
$0 |
$0 |
$0 |
$4,000 |
2 |
20-00 2020 NWI 2020-2024 Transportation Improvement Program |
2023 |
NHPP Non Interstate |
$0 |
$0 |
$901,518 |
$0 |
$901,518 |
2 |
20-00 2020 NWI 2020-2024 Transportation Improvement Program |
2023 |
State Match |
$0 |
$0 |
$225,380 |
$0 |
$225,380 |
|
TOTAL FOR VERSION 2 |
$100,000 |
$0 |
$1,126,898 |
$0 |
$1,226,898 |
|
1 |
18-08 2018 Res 18-13; Amend 16 (Aug); STIP 18-30 |
2020 |
NHPP Non Interstate |
$64,000 |
$0 |
$0 |
$0 |
$64,000 |
1 |
18-08 2018 Res 18-13; Amend 16 (Aug); STIP 18-30 |
2020 |
State Match |
$16,000 |
$0 |
$0 |
$0 |
$16,000 |
1 |
18-08 2018 Res 18-13; Amend 16 (Aug); STIP 18-30 |
2022 |
NHPP Non Interstate |
$16,000 |
$0 |
$0 |
$0 |
$16,000 |
1 |
18-08 2018 Res 18-13; Amend 16 (Aug); STIP 18-30 |
2022 |
State Match |
$4,000 |
$0 |
$0 |
$0 |
$4,000 |
1 |
18-08 2018 Res 18-13; Amend 16 (Aug); STIP 18-30 |
2023 |
NHPP Non Interstate |
$0 |
$0 |
$901,518 |
$0 |
$901,518 |
1 |
18-08 2018 Res 18-13; Amend 16 (Aug); STIP 18-30 |
2023 |
State Match |
$0 |
$0 |
$225,380 |
$0 |
$225,380 |
|
TOTAL FOR VERSION 1 |
$100,000 |
$0 |
$1,126,898 |
$0 |
$1,226,898 |
|
|
|
|
<< Go Back
|
|
Bridge Replacement (1703012)
|
VERSION |
|
PUBLIC DESCRIPTION |
STATUS |
APPROVAL DATE |
3 |
22-00 2022-2026 2022 TIP |
BRIDGE REPLACEMENT |
PROGRAMMED |
|
2 |
20-00 2020 TIP |
BRIDGE REPLACEMENT |
PROGRAMMED |
8/22/19 |
1 |
18-08 Q1 2018 INDOT |
BRIDGE REPLACEMENT |
PROGRAMMED |
10/11/2018 |
|
|
|
|