Pedestrian Bridge replacement (Project ID # NP_INDU_0945) (NP_INDU_0945(1))
|
|
|
|
Phase |
Fund Source
|
Prior SFY |
SFY2022 |
SFY2023 |
SFY2024 |
SFY2025 |
SFY2026 |
Future SFY |
Total |
CN |
FLTP |
- |
$1,000,000
|
-
|
-
|
-
|
-
|
-
|
$1,000,000 |
Total Construction |
- |
$1,000,000 |
- |
- |
- |
- |
- |
$1,000,000 |
Total Programmed |
- |
$1,000,000
|
-
|
-
|
-
|
-
|
-
|
$1,000,000 |
|
Map Coming Soon
Map location not available
|
|
<< Go Back
|
|
Pedestrian Bridge replacement (Project ID # NP_INDU_0945) (NP_INDU_0945(1))
|
VERSION |
SFY |
SOURCE |
PE |
ROW |
CON |
CE |
TOTAL |
3 |
22-04 2022 TIP Amendment March 2022 for 2020-2024 & 2022-2026 TIPs |
2022 |
FLTP |
$0 |
$0 |
$1,000,000 |
$0 |
$1,000,000 |
|
TOTAL FOR VERSION 3 |
$0 |
$0 |
$1,000,000 |
$0 |
$1,000,000 |
|
2 |
20-10.3 2021 September Infrastructure Amendment |
2021 |
FLTP |
$0 |
$0 |
$1,000,000 |
$0 |
$1,000,000 |
|
TOTAL FOR VERSION 2 |
$0 |
$0 |
$1,000,000 |
$0 |
$1,000,000 |
|
1 |
18-18 2018-2021 INTERNAL USE ONLY |
2021 |
FLTP |
$0 |
$0 |
$1,000,000 |
$0 |
$1,000,000 |
|
TOTAL FOR VERSION 1 |
$0 |
$0 |
$1,000,000 |
$0 |
$1,000,000 |
|
|
|
|
<< Go Back
|
|
Pedestrian Bridge replacement (Project ID # NP_INDU_0945) (NP_INDU_0945(1))
|
VERSION |
|
PUBLIC DESCRIPTION |
STATUS |
APPROVAL DATE |
3 |
22-04 April 2022 LOCAL |
PEDESTRIAN BRIDGE REPLACEMENT (PROJECT ID # NP_INDU_0945) |
PROGRAMMED |
04/20/2022 |
2 |
20-10.3 September 2021 LOCAL |
PEDESTRIAN BRIDGE REPLACEMENT (PROJECT ID # NP_INDU_0945) |
PROGRAMMED |
10/06/2020 |
1 |
18-18 2018-2021 ADMIN |
PEDESTRIAN BRIDGE REPLACEMENT |
PROGRAMMED |
N/A |
|
|
|
|