Multi-use paths / Westchester-Liberty Phase 3 (1902832)
Des Number 1902832 Amendment 20-04.3 ADMIN MOD Exempt Category Non-Exempt Est Total Project Cost $1,582,469
Lead Agency Chesterton Contact (ERC) Erdmann, Jami 2193257484 County Porter
Project Type Other Letting Date 02/15/2023 Functional Classification Not Applicable Bike/Ped Component(s) Yes 100%
Title Multi-use paths / Westchester-Liberty Phase 3
Limits Westchester-Liberty from 5th Street to CR 100 E of Distance (mile) 0.98
Description The construction of Phase 3 of the Westchester-Liberty trail will complete the connection between the Prairie Duneland Trail and the Dunes-Kankakee Trail, both of which are High Priority Trails as identified by NIRPC. This project will extend the existing 8-foot the Westchester-Liberty south through an existing park to connect to an existing 8' multi-use trail which will allow the users to safely access the Coffee Creek Watershed Preserve from west of S.R. 49. shared-use Westchester Liberty Trail along County Road (CR) 1100 North from the existing path's termination point on S 5th Street and continue east approximately 2,355 feet to CR 100 E where it will connect to the Dunes Kankakee Trail. This project will also extend the Westchester-Liberty south through an existing park to connect to an existing 8' multi-use trail which will allow the users to safely access the Coffee Creek Watershed Preserve from west of S.R. 49.
Phase Fund Source Prior SFY SFY2020 SFY2021 SFY2022 SFY2023 SFY2024 Future SFY Total
RW Local Fund - - $21,094 - - - - $21,094
RW TAP Chicago UZA - - $84,375 - - - - $84,375
Total Right of Way - - $105,469 - - - - $105,469
CN Local Fund - - - - - $352,000 - $352,000
CN TAP Chicago UZA - - - - - $1,125,000 - $1,125,000
Total Construction - - - - - $1,477,000 - $1,477,000
Total Programmed - - $105,469 - - $1,477,000 - $1,582,469
Map Coming Soon

Map location not available

<< Go Back
Multi-use paths / Westchester-Liberty Phase 3 (1902832)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  4   22-00 2022 2022-2026 TIP adoption   2022   TAP Chicago UZA   $0   $120,000   $0   $0   $120,000  
  4   22-00 2022 2022-2026 TIP adoption   2022   Local Fund   $0   $30,000   $0   $0   $30,000  
  4   22-00 2022 2022-2026 TIP adoption   2023   TAP Chicago UZA   $0   $0   $1,280,000   $0   $1,280,000  
  4   22-00 2022 2022-2026 TIP adoption   2023   Local Fund   $0   $0   $320,000   $0   $320,000  
TOTAL FOR VERSION 4 $0   $150,000   $1,600,000   $0   $1,750,000  
  3   20-12 2021 January 2021 Infrastructure Amendment   2022   TAP Chicago UZA   $0   $120,000   $0   $0   $120,000  
  3   20-12 2021 January 2021 Infrastructure Amendment   2022   Local Fund   $0   $30,000   $0   $0   $30,000  
  3   20-12 2021 January 2021 Infrastructure Amendment   2023   TAP Chicago UZA   $0   $0   $1,280,000   $0   $1,280,000  
  3   20-12 2021 January 2021 Infrastructure Amendment   2023   Local Fund   $0   $0   $320,000   $0   $320,000  
TOTAL FOR VERSION 3 $0   $150,000   $1,600,000   $0   $1,750,000  
  2   20-04.3 2020-2023 November 2019 Administrative Modification   2021   TAP Chicago UZA   $0   $84,375   $0   $0   $84,375  
  2   20-04.3 2020-2023 November 2019 Administrative Modification   2021   Local Fund   $0   $21,094   $0   $0   $21,094  
  2   20-04.3 2020-2023 November 2019 Administrative Modification   2024   TAP Chicago UZA   $0   $0   $1,125,000   $0   $1,125,000  
  2   20-04.3 2020-2023 November 2019 Administrative Modification   2024   Local Fund   $0   $0   $352,000   $0   $352,000  
TOTAL FOR VERSION 2 $0   $105,469   $1,477,000   $0   $1,582,469  
  1   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2021   TAP Chicago UZA   $0   $84,375   $0   $0   $84,375  
  1   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2021   Local Fund   $0   $21,094   $0   $0   $21,094  
  1   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2024   TAP Chicago UZA   $0   $0   $1,125,000   $0   $1,125,000  
  1   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2024   Local Fund   $0   $0   $352,000   $0   $352,000  
TOTAL FOR VERSION 1 $0   $105,469   $1,477,000   $0   $1,582,469  
<< Go Back
Multi-use paths / Westchester-Liberty Phase 3 (1902832)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  4     22-00 2022-2026 2022 TIP    MULTI-USE PATHS / WESTCHESTER-LIBERTY PHASE 3   PROGRAMMED     
  3     20-12 2021 LOCAL   MULTI-USE PATHS / WESTCHESTER-LIBERTY PHASE 3   PROGRAMMED     
  2     20-04.3 2020-2023 ADMIN   MULTI-USE PATHS / WESTCHESTER-LIBERTY PHASE 3   PROGRAMMED   N/A  
  1     20-00 2020 TIP    MULTI-USE PATHS / WESTCHESTER-LIBERTY PHASE 3   PROGRAMMED   8/22/19