Roadway Expansion Kennedy Ave (Phase 3) (1902000)
Des Number 1902000 Amendment 24-00 STIP Exempt Category Non-Exempt Est Total Project Cost $7,760,713
Contract # R-42412 Contact (ERC) Huet, Jeffrey 2193226688 County Lake
Lead Agency Schererville Letting Date 09/02/2026 Functional Classification Minor Arterial Bike/Ped Component(s) Yes 05%
Project Type Existing Roadway Capacity Improvement
Title Roadway Expansion Kennedy Ave (Phase 3)
Limits Nearest Crossstreet: Main St
Description Kennedy Ave Corridor Improvements Phase 3; Oak St to Main St
Phase Fund Source Prior SFY SFY2024 SFY2025 SFY2026 SFY2027 SFY2028 Future SFY Total
PE Local Fund $47,847 - - - - - - $47,847
PE STBG Chicago UZA $191,387 - - - - - - $191,387
Total Preliminary Engineering $239,234 - - - - - - $239,234
RW Local Fund $86,100 - - - - - - $86,100
RW STBG Chicago UZA $344,400 - - - - - - $344,400
Total Right of Way $430,500 - - - - - - $430,500
CN Local Fund - - $1,418,196 - - - - $1,418,196
CN STBG Chicago UZA - - $5,672,783 - - - - $5,672,783
Total Construction - - $7,090,979 - - - - $7,090,979
Total Programmed $669,734 - $7,090,979 - - - - $7,760,713
Map Coming Soon

Map location not available

<< Go Back
Roadway Expansion Kennedy Ave (Phase 3) (1902000)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  5   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2023   STBG Chicago UZA   $191,387   $344,400   $0   $0   $535,787  
  5   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2023   Local Fund   $47,847   $86,100   $0   $0   $133,947  
  5   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   STBG Chicago UZA   $0   $0   $5,672,783   $0   $5,672,783  
  5   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   Local Fund   $0   $0   $1,418,196   $0   $1,418,196  
TOTAL FOR VERSION 5 $239,234   $430,500   $7,090,979   $0   $7,760,713  
  4   22-55 2022 October, 2021 Administrative Modification STIP Modification 20-35   2023   STBG Chicago UZA   $191,387   $344,400   $0   $0   $535,787  
  4   22-55 2022 October, 2021 Administrative Modification STIP Modification 20-35   2023   Local Fund   $47,847   $86,100   $0   $0   $133,947  
  4   22-55 2022 October, 2021 Administrative Modification STIP Modification 20-35   2025   STBG Chicago UZA   $0   $0   $5,672,783   $0   $5,672,783  
  4   22-55 2022 October, 2021 Administrative Modification STIP Modification 20-35   2025   Local Fund   $0   $0   $1,418,196   $0   $1,418,196  
TOTAL FOR VERSION 4 $239,234   $430,500   $7,090,979   $0   $7,760,713  
  3   22-03 2022 TIP Amendment January 2022 for 2020-2024 & 2022-2026 TIPs   2023   STBG Chicago UZA   $191,387   $344,400   $0   $0   $535,787  
  3   22-03 2022 TIP Amendment January 2022 for 2020-2024 & 2022-2026 TIPs   2023   Local Fund   $47,847   $86,100   $0   $0   $133,947  
  3   22-03 2022 TIP Amendment January 2022 for 2020-2024 & 2022-2026 TIPs   2025   STBG Chicago UZA   $0   $0   $5,672,783   $0   $5,672,783  
  3   22-03 2022 TIP Amendment January 2022 for 2020-2024 & 2022-2026 TIPs   2025   Local Fund   $0   $0   $1,418,196   $0   $1,418,196  
TOTAL FOR VERSION 3 $239,234   $430,500   $7,090,979   $0   $7,760,713  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   STBG Chicago UZA   $191,387   $344,400   $0   $0   $535,787  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   Local Fund   $47,847   $86,100   $0   $0   $133,947  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   STBG Chicago UZA   $0   $0   $5,672,783   $0   $5,672,783  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   Local Fund   $0   $0   $1,418,196   $0   $1,418,196  
TOTAL FOR VERSION 2 $239,234   $430,500   $7,090,979   $0   $7,760,713  
  1   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2023   STBG Chicago UZA   $191,387   $344,400   $0   $0   $535,787  
  1   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2023   Local Fund   $47,847   $86,100   $0   $0   $133,947  
  1   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2025   STBG Chicago UZA   $0   $0   $5,672,783   $0   $5,672,783  
  1   20-00 2020 NWI 2020-2024 Transportation Improvement Program   2025   Local Fund   $0   $0   $1,418,196   $0   $1,418,196  
TOTAL FOR VERSION 1 $239,234   $430,500   $7,090,979   $0   $7,760,713  
<< Go Back
Roadway Expansion Kennedy Ave (Phase 3) (1902000)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  5     24-00 July 2024-2027 TIP    ROADWAY EXPANSION KENNEDY AVE (PHASE 3)   PROGRAMMED     
  4     22-55 October 2022 ADMIN   ROADWAY EXPANSION KENNEDY AVE (PHASE 3)   PROGRAMMED   N/A  
  3     22-03 January 2022 LOCAL   ROADWAY EXPANSION KENNEDY AVE (PHASE 3)   PROGRAMMED   4/20/2022  
  2     22-00 2022-2026 2022 TIP    ROADWAY EXPANSION KENNEDY AVE   PROGRAMMED   06/17/2022  
  1     20-00 2020 TIP    ROADWAY EXPANSION KENNEDY AVE   PROGRAMMED   8/22/19