Veteran's Memorial Trail (P1) (1902675)
Des Number 1902675 Amendment 24-00 STIP Exempt Category Exempt Est Total Project Cost $1,742,754
Contract # Contact (ERC) Alverson, Duane 2196630525 County Lake
Lead Agency Lake County Letting Date Functional Classification Not Applicable Bike/Ped Component(s) Yes 100%
Project Type Bicycle Enhancement
Title Veteran's Memorial Trail (P1)
Limits Nearest Crossstreet:
Description Veteran's Memorial Trail (Phase 1), from Crown Point Sportsplex (113th & US 231) to Delaware Parkway
Phase Fund Source Prior SFY SFY2024 SFY2025 SFY2026 SFY2027 SFY2028 Future SFY Total
PE Local Fund $400,000 - - - - - - $400,000
Total Preliminary Engineering $400,000 - - - - - - $400,000
CN Local Fund - - - $242,562 - - - $242,562
CN STBG Chicago UZA - - - $970,248 - - - $970,248
Total Construction - - - $1,212,810 - - - $1,212,810
CE Local Fund - - - $25,989 - - - $25,989
CE STBG Chicago UZA - - - $103,955 - - - $103,955
Total Construction Engineering - - - $129,944 - - - $129,944
Total Programmed $400,000 - - $1,342,754 - - - $1,742,754
Map Coming Soon

Map location not available

<< Go Back
Veteran's Memorial Trail (P1) (1902675)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  4   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2021   Local Fund   $400,000   $0   $0   $0   $400,000  
  4   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2026   STBG Chicago UZA   $0   $0   $970,248   $0   $1,074,203  
  4   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2026   Local Fund   $0   $0   $242,562   $0   $268,551  
TOTAL FOR VERSION 4 $400,000   $0   $1,212,810   $0   $1,742,754  
  3   22-15 2021 Admin Mod to add total costs to project missing phases.   2021   Local Fund   $400,000   $0   $0   $0   $400,000  
  3   22-15 2021 Admin Mod to add total costs to project missing phases.   2024   STBG Chicago UZA   $0   $0   $970,248   $0   $1,074,203  
  3   22-15 2021 Admin Mod to add total costs to project missing phases.   2024   Local Fund   $0   $0   $242,562   $0   $268,551  
TOTAL FOR VERSION 3 $400,000   $0   $1,212,810   $0   $1,742,754  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   STBG Chicago UZA   $0   $0   $970,248   $0   $1,074,203  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   Local Fund   $0   $0   $242,562   $0   $268,551  
TOTAL FOR VERSION 2 $0   $0   $1,212,810   $0   $1,342,754  
  1   20-03 2020 November 2019 Amendment #2   2024   STBG Chicago UZA   $0   $0   $970,248   $0   $1,074,203  
  1   20-03 2020 November 2019 Amendment #2   2024   Local Fund   $0   $0   $242,562   $0   $268,551  
TOTAL FOR VERSION 1 $0   $0   $1,212,810   $0   $1,342,754  
<< Go Back
Veteran's Memorial Trail (P1) (1902675)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  4     24-00 July 2024-2027 TIP    VETERAN'S MEMORIAL TRAIL (P1)   PROGRAMMED     
  3     22-15 July 2021 ADMIN   VETERAN'S MEMORIAL TRAIL (P1)   PROGRAMMED   N/A  
  2     22-00 2022-2026 2022 TIP    VETERAN'S MEMORIAL TRAIL (P1)   PROGRAMMED   06/17/2022  
  1     20-03 2020 INDOT   VETERAN'S MEMORIAL TRAIL (P1)   PROGRAMMED   1/24/2020