District Bridge Project (1900009)
Des Number 1900009 Amendment 24-00 STIP Exempt Category Exempt Est Total Project Cost $4,589,364
Contract # Contact (ERC) County Lake
Lead Agency INDOT Letting Date 07/10/2024 Functional Classification Other Principal Arterial Bike/Ped Component(s) No
Project Type Bridge Replacement, Concrete
Title District Bridge Project
Limits
Description Bridge Replacement, Concrete, US 20 at Kennedy Ave, IHB RR, 0.99mi E of SR 152.
Phase Fund Source Prior SFY SFY2024 SFY2025 SFY2026 SFY2027 SFY2028 Future SFY Total
PE STBG State - - $252,000 - - - - $252,000
PE State Match $420,000 - $63,000 - - - - $483,000
Total Preliminary Engineering $420,000 - $315,000 - - - - $735,000
CN STBG State - - $3,063,491 - - - - $3,063,491
CN State Match - $25,000 $765,873 - - - - $790,873
Total Construction - $25,000 $3,829,364 - - - - $3,854,364
Total Programmed $420,000 $25,000 $4,144,364 - - - - $4,589,364
Map Coming Soon

Map location not available

<< Go Back
District Bridge Project (1900009)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2021   State Match   $420,000   $0   $0   $0   $420,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2024   State Match   $0   $0   $25,000   $0   $25,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   STBG State   $252,000   $0   $3,063,491   $0   $3,315,491  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   State Match   $63,000   $0   $765,873   $0   $828,873  
TOTAL FOR VERSION 3 $735,000   $0   $3,854,364   $0   $4,589,364  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2021   State Match   $420,000   $0   $0   $0   $420,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   State Match   $0   $0   $25,000   $0   $25,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   STBG State   $252,000   $0   $3,063,491   $0   $3,315,491  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   State Match   $63,000   $0   $765,873   $0   $828,873  
TOTAL FOR VERSION 2 $735,000   $0   $3,854,364   $0   $4,589,364  
  1   20-07 2020 Amendment 20-03 April 2020   2021   State Match   $420,000   $0   $0   $0   $420,000  
  1   20-07 2020 Amendment 20-03 April 2020   2023   State Match   $0   $0   $15,000   $0   $15,000  
  1   20-07 2020 Amendment 20-03 April 2020   2024   STBG State   $0   $0   $3,319,141   $0   $3,589,141  
TOTAL FOR VERSION 1 $420,000   $0   $3,334,141   $0   $4,024,141  
<< Go Back
District Bridge Project (1900009)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  3     24-00 July 2024-2027 TIP    DISTRICT BRIDGE PROJECT   PROGRAMMED     
  2     22-00 2022-2026 2022 TIP    DISTRICT BRIDGE PROJECT   PROGRAMMED   06/17/2022  
  1     20-07 2020 LOCAL   DISTRICT BRIDGE PROJECT   PROGRAMMED   8/3/20