District Bridge Project (1900012)
Des Number 1900012 Amendment 22-00 STIP Exempt Category Exempt Est Total Project Cost $4,287,589
Contract # Contact (ERC) County Lake
Lead Agency INDOT Letting Date 08/09/2023 Functional Classification Other Principal Arterial Bike/Ped Component(s) No
Project Type Bridge Replacement, Concrete
Title District Bridge Project
Limits
Description Bridge Replacement, Concrete, US 6 at Muck Pocket, 0.84mi E of SR 51/I-80/94
Phase Fund Source Prior SFY SFY2022 SFY2023 SFY2024 SFY2025 SFY2026 Future SFY Total
PE STBG State - - - $248,000 - - - $248,000
PE State Match $485,000 - - $62,000 - - - $547,000
Total Preliminary Engineering $485,000 - - $310,000 - - - $795,000
CN STBG State - - - $2,782,071 - - - $2,782,071
CN State Match - - - $695,518 - - - $695,518
CN State Special Projects - - $15,000 - - - - $15,000
Total Construction - - $15,000 $3,477,589 - - - $3,492,589
Total Programmed $485,000 - $15,000 $3,787,589 - - - $4,287,589
Map Coming Soon

Map location not available

<< Go Back
District Bridge Project (1900012)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2021   State Match   $485,000   $0   $0   $0   $485,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   State Special Projects   $0   $0   $15,000   $0   $15,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   STBG State   $248,000   $0   $2,782,071   $0   $3,030,071  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   State Match   $62,000   $0   $695,518   $0   $757,518  
TOTAL FOR VERSION 2 $795,000   $0   $3,492,589   $0   $4,287,589  
  1   20-07 2020 Amendment 20-03 April 2020   2021   State Match   $485,000   $0   $0   $0   $485,000  
  1   20-07 2020 Amendment 20-03 April 2020   2023   State Match   $0   $0   $15,000   $0   $15,000  
  1   20-07 2020 Amendment 20-03 April 2020   2024   STBG State   $0   $0   $3,477,589   $0   $3,787,589  
TOTAL FOR VERSION 1 $485,000   $0   $3,492,589   $0   $4,287,589  
<< Go Back
District Bridge Project (1900012)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  2     22-00 2022-2026 2022 TIP    DISTRICT BRIDGE PROJECT   PROGRAMMED   06/17/2022  
  1     20-07 2020 LOCAL   DISTRICT BRIDGE PROJECT   PROGRAMMED   8/3/20