District Small Structure Project (1900016)
Des Number 1900016 Amendment 24-00 STIP Exempt Category Exempt Est Total Project Cost $1,081,368
Contract # Contact (ERC) County Porter
Lead Agency INDOT Letting Date 10/12/2023 Functional Classification Other Principal Arterial Bike/Ped Component(s) No
Project Type Small Structure Replacement
Title District Small Structure Project
Limits
Description Small Structure Replacement, SR 2, 2.65mi W JCT of US 30. Includes 2 other des numbers.
Phase Fund Source Prior SFY SFY2024 SFY2025 SFY2026 SFY2027 SFY2028 Future SFY Total
PE STBG State - $55,920 - - - - - $55,920
PE State Match $195,000 $13,980 - - - - - $208,980
Total Preliminary Engineering $195,000 $69,900 - - - - - $264,900
CN STBG State - $629,175 - - - - - $629,175
CN State Match - $157,293 - - - - - $157,293
CN State Special Projects $30,000 - - - - - - $30,000
Total Construction $30,000 $786,468 - - - - - $816,468
Total Programmed $225,000 $856,368 - - - - - $1,081,368
Map Coming Soon

Map location not available

<< Go Back
District Small Structure Project (1900016)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2021   State Match   $195,000   $0   $0   $0   $195,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2023   State Special Projects   $0   $0   $30,000   $0   $30,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2024   State Match   $13,980   $0   $157,293   $0   $171,273  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2024   STBG State   $55,920   $0   $629,175   $0   $685,095  
TOTAL FOR VERSION 3 $264,900   $0   $816,468   $0   $1,081,368  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2021   State Match   $195,000   $0   $0   $0   $195,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   State Special Projects   $0   $0   $30,000   $0   $30,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   STBG State   $55,920   $0   $629,175   $0   $685,095  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   State Match   $13,980   $0   $157,293   $0   $171,273  
TOTAL FOR VERSION 2 $264,900   $0   $816,468   $0   $1,081,368  
  1   20-07 2020 Amendment 20-03 April 2020   2021   State Match   $195,000   $0   $0   $0   $195,000  
  1   20-07 2020 Amendment 20-03 April 2020   2023   State Match   $0   $0   $10,000   $0   $10,000  
  1   20-07 2020 Amendment 20-03 April 2020   2024   STBG State   $0   $0   $310,537   $0   $338,137  
TOTAL FOR VERSION 1 $195,000   $0   $320,537   $0   $543,137  
<< Go Back
District Small Structure Project (1900016)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  3     24-00 July 2024-2027 TIP    DISTRICT SMALL STRUCTURE PROJECT   PROGRAMMED     
  2     22-00 2022-2026 2022 TIP    DISTRICT SMALL STRUCTURE PROJECT   PROGRAMMED   06/17/2022  
  1     20-07 2020 LOCAL   DISTRICT SMALL STRUCTURE PROJECT   PROGRAMMED   8/3/20