District Pavement Project (1900055)
Des Number 1900055 Amendment 24-00 STIP Exempt Category Exempt Est Total Project Cost $7,184,677
Contract # Contact (ERC) County Lake
Lead Agency INDOT Letting Date Functional Classification Other Principal Arterial Bike/Ped Component(s) No
Project Type HMA Overlay Minor Structural
Title District Pavement Project
Limits
Description HMA Overlay Minor Structural, US 30 from 0.37mi E of I-65 to SR 51.
Phase Fund Source Prior SFY SFY2024 SFY2025 SFY2026 SFY2027 SFY2028 Future SFY Total
PE State Match $873,800 - - - - - - $873,800
Total Preliminary Engineering $873,800 - - - - - - $873,800
CN NHPP Non Interstate - $5,941,077 - - - - - $5,941,077
CN State Match $10,000 - - - - - - $10,000
Total Construction $10,000 $5,941,077 - - - - - $5,951,077
CE NHPP Non Interstate - $359,800 - - - - - $359,800
Total Construction Engineering - $359,800 - - - - - $359,800
Total Programmed $883,800 $6,300,877 - - - - - $7,184,677
Map Coming Soon

Map location not available

<< Go Back
District Pavement Project (1900055)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2021   State Match   $873,800   $0   $0   $0   $873,800  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2023   State Match   $0   $0   $10,000   $0   $10,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2024   NHPP Non Interstate   $0   $0   $5,941,077   $0   $6,300,877  
TOTAL FOR VERSION 3 $873,800   $0   $5,951,077   $0   $7,184,677  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2021   State Match   $873,800   $0   $0   $0   $873,800  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   State Match   $0   $0   $10,000   $0   $10,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   NHPP Non Interstate   $0   $0   $5,941,077   $0   $6,300,877  
TOTAL FOR VERSION 2 $873,800   $0   $5,951,077   $0   $7,184,677  
  1   20-07 2020 Amendment 20-03 April 2020   2021   State Match   $873,800   $0   $0   $0   $873,800  
  1   20-07 2020 Amendment 20-03 April 2020   2023   State Match   $0   $0   $10,000   $0   $10,000  
  1   20-07 2020 Amendment 20-03 April 2020   2024   NHPP Non Interstate   $0   $0   $5,941,077   $0   $6,300,877  
TOTAL FOR VERSION 1 $873,800   $0   $5,951,077   $0   $7,184,677  
<< Go Back
District Pavement Project (1900055)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  3     24-00 July 2024-2027 TIP    DISTRICT PAVEMENT PROJECT   PROGRAMMED     
  2     22-00 2022-2026 2022 TIP    DISTRICT PAVEMENT PROJECT   PROGRAMMED   06/17/2022  
  1     20-07 2020 LOCAL   DISTRICT PAVEMENT PROJECT   PROGRAMMED   8/3/20