District Bridge Project (Rehabilitation) (2000402)
VERSION
SFY
SOURCE
PE
ROW
CON
CE
TOTAL
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2021
State Match
$120,000
$0
$0
$0
$120,000
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2022
State Match
$0
$0
$70,000
$0
$70,000
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2023
State Match
$0
$0
$5,000
$0
$5,000
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2024
NHPP Non Interstate
$0
$0
$336,327
$0
$386,327
TOTAL FOR VERSION 3
$120,000
$0
$411,327
$0
$581,327
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2021
State Match
$120,000
$0
$0
$0
$120,000
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2022
State Match
$0
$0
$70,000
$0
$70,000
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2023
State Match
$0
$0
$5,000
$0
$5,000
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.