District Bridge Project (Rehabilitation) (2000397)
VERSION
SFY
SOURCE
PE
ROW
CON
CE
TOTAL
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2021
State Match
$175,000
$0
$0
$0
$175,000
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2023
State Special Projects
$0
$0
$5,000
$0
$5,000
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2024
NHPP Non Interstate
$40,000
$0
$344,143
$0
$384,143
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2024
State Match
$10,000
$0
$86,036
$0
$96,036
TOTAL FOR VERSION 3
$225,000
$0
$435,179
$0
$660,179
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2021
State Match
$175,000
$0
$0
$0
$175,000
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2023
State Special Projects
$0
$0
$5,000
$0
$5,000
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2024
NHPP Non Interstate
$40,000
$0
$344,143
$0
$384,143
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.