District Bridge Project (Rehabilitation) (2000819)
VERSION
SFY
SOURCE
PE
ROW
CON
CE
TOTAL
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2021
State Match
$83,700
$0
$0
$0
$83,700
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2023
State Special Projects
$0
$0
$40,000
$0
$40,000
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2024
NHPP Non Interstate
$68,000
$0
$1,035,618
$0
$1,103,618
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2024
State Match
$17,000
$0
$258,904
$0
$275,904
TOTAL FOR VERSION 3
$168,700
$0
$1,334,522
$0
$1,503,222
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2021
State Match
$83,700
$0
$0
$0
$83,700
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2023
State Special Projects
$0
$0
$40,000
$0
$40,000
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2024
NHPP Non Interstate
$68,000
$0
$1,035,618
$0
$1,103,618
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.