District Bridge Project (Rehabilitation) (2000770)
Des Number 2000770 Amendment 24-00 STIP Exempt Category Exempt Est Total Project Cost $1,141,984
Contract # Contact (ERC) County Lake
Lead Agency INDOT Letting Date Functional Classification Interstate Bike/Ped Component(s) No
Project Type Bridge Thin Deck Overlay
Title District Bridge Project (Rehabilitation)
Limits
Description Bridge Thin Deck Overlay, I 80 WBL over CONRAIL RR, IHB RR, 00.70 E US 41
Phase Fund Source Prior SFY SFY2024 SFY2025 SFY2026 SFY2027 SFY2028 Future SFY Total
PE State Match $106,500 - - - - - - $106,500
Total Preliminary Engineering $106,500 - - - - - - $106,500
CN NHPP Interstate - $859,484 - - - - - $859,484
CN State Match $105,000 - - - - - - $105,000
Total Construction $105,000 $859,484 - - - - - $964,484
CE NHPP Interstate - $71,000 - - - - - $71,000
Total Construction Engineering - $71,000 - - - - - $71,000
Total Programmed $211,500 $930,484 - - - - - $1,141,984
Map Coming Soon

Map location not available

<< Go Back
District Bridge Project (Rehabilitation) (2000770)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2021   State Match   $106,500   $0   $0   $0   $106,500  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2023   State Match   $0   $0   $105,000   $0   $105,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2024   NHPP Interstate   $0   $0   $859,484   $0   $930,484  
TOTAL FOR VERSION 3 $106,500   $0   $964,484   $0   $1,141,984  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2021   State Match   $106,500   $0   $0   $0   $106,500  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   State Match   $0   $0   $105,000   $0   $105,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   NHPP Interstate   $0   $0   $859,484   $0   $930,484  
TOTAL FOR VERSION 2 $106,500   $0   $964,484   $0   $1,141,984  
  1   20-09 2021 July 2020 Amendment #9   2021   State Match   $106,500   $0   $0   $0   $106,500  
  1   20-09 2021 July 2020 Amendment #9   2023   State Match   $0   $0   $105,000   $0   $105,000  
  1   20-09 2021 July 2020 Amendment #9   2024   NHPP Interstate   $0   $0   $859,484   $0   $930,484  
TOTAL FOR VERSION 1 $106,500   $0   $964,484   $0   $1,141,984  
<< Go Back
District Bridge Project (Rehabilitation) (2000770)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  3     24-00 July 2024-2027 TIP    DISTRICT BRIDGE PROJECT (REHABILITATION)   PROGRAMMED     
  2     22-00 2022-2026 2022 TIP    DISTRICT BRIDGE PROJECT (REHABILITATION)   PROGRAMMED   06/17/2022  
  1     20-09 July 2021 LOCAL   DISTRICT BRIDGE PROJECT (REHABILITATION)   PROGRAMMED   08/03/2020