HGAC
  • Project Overview
  • Funding History
  • Amendment History
<< Go Back
District Bridge Project (Rehabilitation) (2000777)
Des Number 2000777 Amendment 24-00 STIP Exempt Category Exempt Est Total Project Cost $1,006,181
Contract # Contact (ERC) County Lake
Lead Agency INDOT Letting Date Functional Classification Interstate Bike/Ped Component(s) No
Project Type Bridge Deck Overlay
Title District Bridge Project (Rehabilitation)
Limits
Description Bridge Deck Overlay, I 80 EB over SR 912 EB/WB, RAMPS, 02.54 E US 41
Phase Fund Source Prior SFY SFY2024 SFY2025 SFY2026 SFY2027 SFY2028 Future SFY Total
PE State Match $200,000 - - - - - - $200,000
Total Preliminary Engineering $200,000 - - - - - - $200,000
CN NHPP Interstate - $751,181 - - - - - $751,181
CN State Match $5,000 - - - - - - $5,000
Total Construction $5,000 $751,181 - - - - - $756,181
CE NHPP Interstate - $50,000 - - - - - $50,000
Total Construction Engineering - $50,000 - - - - - $50,000
Total Programmed $205,000 $801,181 - - - - - $1,006,181
Map Coming Soon

Map location not available

<< Go Back
District Bridge Project (Rehabilitation) (2000777)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2021   State Match   $200,000   $0   $0   $0   $200,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2023   State Match   $0   $0   $5,000   $0   $5,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2024   NHPP Interstate   $0   $0   $751,181   $0   $801,181  
TOTAL FOR VERSION 3 $200,000   $0   $756,181   $0   $1,006,181  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2021   State Match   $200,000   $0   $0   $0   $200,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   State Match   $0   $0   $5,000   $0   $5,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   NHPP Interstate   $0   $0   $751,181   $0   $801,181  
TOTAL FOR VERSION 2 $200,000   $0   $756,181   $0   $1,006,181  
  1   20-09 2021 July 2020 Amendment #9   2021   State Match   $200,000   $0   $0   $0   $200,000  
  1   20-09 2021 July 2020 Amendment #9   2023   State Match   $0   $0   $5,000   $0   $5,000  
  1   20-09 2021 July 2020 Amendment #9   2024   NHPP Interstate   $0   $0   $751,181   $0   $801,181  
TOTAL FOR VERSION 1 $200,000   $0   $756,181   $0   $1,006,181  
<< Go Back
District Bridge Project (Rehabilitation) (2000777)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  3     24-00 July 2024-2027 TIP    DISTRICT BRIDGE PROJECT (REHABILITATION)   PROGRAMMED     
  2     22-00 2022-2026 2022 TIP    DISTRICT BRIDGE PROJECT (REHABILITATION)   PROGRAMMED   06/17/2022  
  1     20-09 July 2021 LOCAL   DISTRICT BRIDGE PROJECT (REHABILITATION)   PROGRAMMED   08/03/2020