District Bridge Project (Rehabilitation) (2000396)
Des Number 2000396 Amendment 24-00 STIP Exempt Category Exempt Est Total Project Cost $622,254
Contract # Contact (ERC) County Lake
Lead Agency INDOT Letting Date Functional Classification Minor Arterial Bike/Ped Component(s) No
Project Type Bridge Deck Overlay
Title District Bridge Project (Rehabilitation)
Limits
Description Bridge Deck Overlay, SR 55 over GRIESEL DITCH, 02.05 S SR 2
Phase Fund Source Prior SFY SFY2024 SFY2025 SFY2026 SFY2027 SFY2028 Future SFY Total
PE State Match $175,000 - - - - - - $175,000
Total Preliminary Engineering $175,000 - - - - - - $175,000
CN NHPP Non Interstate - $392,254 - - - - - $392,254
CN State Match $5,000 - - - - - - $5,000
Total Construction $5,000 $392,254 - - - - - $397,254
CE NHPP Non Interstate - $50,000 - - - - - $50,000
Total Construction Engineering - $50,000 - - - - - $50,000
Total Programmed $180,000 $442,254 - - - - - $622,254
Map Coming Soon

Map location not available

<< Go Back
District Bridge Project (Rehabilitation) (2000396)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2021   State Match   $175,000   $0   $0   $0   $175,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2023   State Match   $0   $0   $5,000   $0   $5,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2024   NHPP Non Interstate   $0   $0   $392,254   $0   $442,254  
TOTAL FOR VERSION 3 $175,000   $0   $397,254   $0   $622,254  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2021   State Match   $175,000   $0   $0   $0   $175,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   State Match   $0   $0   $5,000   $0   $5,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   NHPP Non Interstate   $0   $0   $392,254   $0   $442,254  
TOTAL FOR VERSION 2 $175,000   $0   $397,254   $0   $622,254  
  1   20-09 2021 July 2020 Amendment #9   2021   State Match   $175,000   $0   $0   $0   $175,000  
  1   20-09 2021 July 2020 Amendment #9   2023   State Match   $0   $0   $5,000   $0   $5,000  
  1   20-09 2021 July 2020 Amendment #9   2024   NHPP Non Interstate   $0   $0   $392,254   $0   $442,254  
TOTAL FOR VERSION 1 $175,000   $0   $397,254   $0   $622,254  
<< Go Back
District Bridge Project (Rehabilitation) (2000396)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  3     24-00 July 2024-2027 TIP    DISTRICT BRIDGE PROJECT (REHABILITATION)   PROGRAMMED     
  2     22-00 2022-2026 2022 TIP    DISTRICT BRIDGE PROJECT (REHABILITATION)   PROGRAMMED   06/17/2022  
  1     20-09 July 2021 LOCAL   DISTRICT BRIDGE PROJECT (REHABILITATION)   PROGRAMMED   08/03/2020