District Bridge Project (Rehabilitation) (2000419)
Des Number 2000419 Amendment 22-00 STIP Exempt Category Exempt Est Total Project Cost $1,023,952
Contract # Contact (ERC) County Porter
Lead Agency INDOT Letting Date Functional Classification Interstate Bike/Ped Component(s) No
Project Type Bridge Thin Deck Overlay
Title District Bridge Project (Rehabilitation)
Limits
Description Bridge Thin Deck Overlay, I 94 EB over LITTLE CALUMET RIVER, 01.54 W SR 49
Phase Fund Source Prior SFY SFY2022 SFY2023 SFY2024 SFY2025 SFY2026 Future SFY Total
PE State Match $200,000 - - - - - - $200,000
Total Preliminary Engineering $200,000 - - - - - - $200,000
CN NHPP Interstate - - - $793,952 - - - $793,952
CN State Match - - $5,000 - - - - $5,000
Total Construction - - $5,000 $793,952 - - - $798,952
CE NHPP Interstate - - - $25,000 - - - $25,000
Total Construction Engineering - - - $25,000 - - - $25,000
Total Programmed $200,000 - $5,000 $818,952 - - - $1,023,952
Map Coming Soon

Map location not available

<< Go Back
District Bridge Project (Rehabilitation) (2000419)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2021   State Match   $200,000   $0   $0   $0   $200,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   State Match   $0   $0   $5,000   $0   $5,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   NHPP Interstate   $0   $0   $793,952   $0   $818,952  
TOTAL FOR VERSION 2 $200,000   $0   $798,952   $0   $1,023,952  
  1   20-09 2021 July 2020 Amendment #9   2021   State Match   $200,000   $0   $0   $0   $200,000  
  1   20-09 2021 July 2020 Amendment #9   2023   State Match   $0   $0   $5,000   $0   $5,000  
  1   20-09 2021 July 2020 Amendment #9   2024   NHPP Interstate   $0   $0   $793,952   $0   $818,952  
TOTAL FOR VERSION 1 $200,000   $0   $798,952   $0   $1,023,952  
<< Go Back
District Bridge Project (Rehabilitation) (2000419)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  2     22-00 2022-2026 2022 TIP    DISTRICT BRIDGE PROJECT (REHABILITATION)   PROGRAMMED   06/17/2022  
  1     20-09 July 2021 LOCAL   DISTRICT BRIDGE PROJECT (REHABILITATION)   PROGRAMMED   08/03/2020