District Bridge Project (Rehabilitation) in Porter County (2001994)
VERSION
SFY
SOURCE
PE
ROW
CON
CE
TOTAL
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2022
NHPP Non Interstate
$28,800
$0
$0
$0
$28,800
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2022
State Match
$7,200
$0
$0
$0
$7,200
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2024
NHPP Non Interstate
$0
$0
$32,000
$0
$32,000
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2024
State Match
$0
$0
$8,000
$0
$8,000
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2025
NHPP Non Interstate
$24,000
$0
$214,133
$0
$238,133
3
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2025
State Match
$6,000
$0
$53,533
$0
$59,533
TOTAL FOR VERSION 3
$66,000
$0
$307,666
$0
$373,666
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2022
NHPP Non Interstate
$28,800
$0
$0
$0
$28,800
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2022
State Match
$7,200
$0
$0
$0
$7,200
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2024
NHPP Non Interstate
$0
$0
$32,000
$0
$32,000
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2024
State Match
$0
$0
$8,000
$0
$8,000
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2025
NHPP Non Interstate
$24,000
$0
$214,133
$0
$238,133
2
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2025
State Match
$6,000
$0
$53,533
$0
$59,533
TOTAL FOR VERSION 2
$66,000
$0
$307,666
$0
$373,666
1
20-12 2021 January 2021 Infrastructure Amendment; STIP Amend # 20-54
2022
State Match
$36,000
$0
$0
$0
$36,000
1
20-12 2021 January 2021 Infrastructure Amendment; STIP Amend # 20-54
2024
NHPP Non Interstate
$0
$0
$40,000
$0
$40,000
1
20-12 2021 January 2021 Infrastructure Amendment; STIP Amend # 20-54