HGAC
  • Project Overview
  • Funding History
  • Amendment History
<< Go Back
District Pavement Project (Non-I) in Lake County (2002312)
Des Number 2002312 Amendment 24-00 STIP Exempt Category Exempt Est Total Project Cost $5,909,664
Contract # R-43386 Contact (ERC) County Lake
Lead Agency INDOT Letting Date Functional Classification Other Principal Arterial Bike/Ped Component(s) No
Project Type HMA Overlay Minor Structural
Title District Pavement Project (Non-I) in Lake County
Limits
Description HMA Overlay Minor Structural, US 20 US 12 (Columbus Ave.) to SR 152
Phase Fund Source Prior SFY SFY2024 SFY2025 SFY2026 SFY2027 SFY2028 Future SFY Total
PE NHPP Non Interstate $280,000 - - - - - - $280,000
PE State Match $70,000 - - - - - - $70,000
Total Preliminary Engineering $350,000 - - - - - - $350,000
RW NHPP Non Interstate $80,000 - - - - - - $80,000
RW State Match $20,000 - - - - - - $20,000
Total Right of Way $100,000 - - - - - - $100,000
CN NHPP Non Interstate $124,000 $124,000 $4,119,731 - - - - $4,367,731
CN State Match $31,000 $31,000 $1,029,933 - - - - $1,091,933
Total Construction $155,000 $155,000 $5,149,664 - - - - $5,459,664
Total Programmed $605,000 $155,000 $5,149,664 - - - - $5,909,664
Map Coming Soon

Map location not available

<< Go Back
District Pavement Project (Non-I) in Lake County (2002312)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2022   NHPP Non Interstate   $280,000   $0   $0   $0   $280,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2022   State Match   $70,000   $20,000   $0   $0   $90,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2023   NHPP Non Interstate   $0   $80,000   $124,000   $0   $204,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2023   State Match   $0   $0   $31,000   $0   $31,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2024   NHPP Non Interstate   $0   $0   $124,000   $0   $124,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2024   State Match   $0   $0   $31,000   $0   $31,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   NHPP Non Interstate   $0   $0   $4,119,731   $0   $4,119,731  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   State Match   $0   $0   $1,029,933   $0   $1,029,933  
TOTAL FOR VERSION 3 $350,000   $100,000   $5,459,664   $0   $5,909,664  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2022   NHPP Non Interstate   $280,000   $0   $0   $0   $280,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2022   State Match   $70,000   $20,000   $0   $0   $90,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   NHPP Non Interstate   $0   $80,000   $124,000   $0   $204,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   State Match   $0   $0   $31,000   $0   $31,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   NHPP Non Interstate   $0   $0   $124,000   $0   $124,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   State Match   $0   $0   $31,000   $0   $31,000  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   NHPP Non Interstate   $0   $0   $4,119,731   $0   $4,119,731  
  2   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   State Match   $0   $0   $1,029,933   $0   $1,029,933  
TOTAL FOR VERSION 2 $350,000   $100,000   $5,459,664   $0   $5,909,664  
  1   20-12 2021 January 2021 Infrastructure Amendment; STIP Amend # 20-54   2022   State Match   $250,000   $0   $0   $0   $250,000  
  1   20-12 2021 January 2021 Infrastructure Amendment; STIP Amend # 20-54   2023   NHPP Non Interstate   $0   $100,000   $155,000   $0   $255,000  
  1   20-12 2021 January 2021 Infrastructure Amendment; STIP Amend # 20-54   2024   NHPP Non Interstate   $0   $0   $150,000   $0   $150,000  
  1   20-12 2021 January 2021 Infrastructure Amendment; STIP Amend # 20-54   2025   NHPP Non Interstate   $0   $0   $4,499,664   $0   $4,499,664  
TOTAL FOR VERSION 1 $250,000   $100,000   $4,804,664   $0   $5,154,664  
<< Go Back
District Pavement Project (Non-I) in Lake County (2002312)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  3     24-00 July 2024-2027 TIP    DISTRICT PAVEMENT PROJECT (NON-I) IN LAKE COUNTY   PROGRAMMED     
  2     22-00 2022-2026 2022 TIP    DISTRICT PAVEMENT PROJECT (NON-I) IN LAKE COUNTY   PROGRAMMED   06/17/2022  
  1     20-12 2021 LOCAL   DISTRICT PAVEMENT PROJECT (NON-I) IN LAKE COUNTY   PROGRAMMED   02/09/2021