Welcome Center Renovation (1902735)
Des Number 1902735 Amendment 22-00 STIP Exempt Category Exempt Est Total Project Cost $23,031,615
Contract # Contact (ERC) County LaPorte
Lead Agency INDOT Letting Date Functional Classification Not Applicable Bike/Ped Component(s) No
Project Type Rest Area Modernization
Title Welcome Center Renovation
Limits
Description Michigan City Welcome Center Renovation
Phase Fund Source Prior SFY SFY2022 SFY2023 SFY2024 SFY2025 SFY2026 Future SFY Total
PE STBG State - - - $1,406,534 - - - $1,406,534
PE State Match - - - $156,281 - - - $156,281
Total Preliminary Engineering - - - $1,562,815 - - - $1,562,815
CN STBG State - - - - $19,321,920 - - $19,321,920
CN State Match - - - - $2,146,880 - - $2,146,880
Total Construction - - - - $21,468,800 - - $21,468,800
Total Programmed - - - $1,562,815 $21,468,800 - - $23,031,615
Map Coming Soon

Map location not available

<< Go Back
Welcome Center Renovation (1902735)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   STBG State   $1,406,534   $0   $0   $0   $1,406,534  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2024   State Match   $156,281   $0   $0   $0   $156,281  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   State Match   $0   $0   $2,146,880   $0   $2,146,880  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   STBG State   $0   $0   $19,321,920   $0   $19,321,920  
TOTAL FOR VERSION 1 $1,562,815   $0   $21,468,800   $0   $23,031,615  
<< Go Back
Welcome Center Renovation (1902735)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  1     22-00 2022-2026 2022 TIP    WELCOME CENTER RENOVATION   PROGRAMMED   06/17/2022