HGAC
  • Project Overview
  • Funding History
  • Amendment History
<< Go Back
Complete Streets sidewalks on 133rd and Morris (2101110)
Des Number 2101110 Amendment 24-00 STIP Exempt Category Exempt Est Total Project Cost $2,326,625
Contract # R-43999 Contact (ERC) Jill Murr 219-374-7400 County Lake
Lead Agency Cedar Lake Letting Date Functional Classification Minor Arterial Bike/Ped Component(s) Yes 100%
Project Type Pedestrian Enhancement
Title Complete Streets sidewalks on 133rd and Morris
Limits Nearest Crossstreet: Cline
Description Construction of sidewalk along 133rd Ave and Morris from Cline Ave to to the town park and facilities on east side of the lake.
Phase Fund Source Prior SFY SFY2024 SFY2025 SFY2026 SFY2027 SFY2028 Future SFY Total
PE CMAQ Chicago UZA $110,000 - - - - - - $110,000
PE Local Fund $27,500 - - - - - - $27,500
Total Preliminary Engineering $137,500 - - - - - - $137,500
CN Local Fund - - $437,825 - - - - $437,825
CN STBG Chicago UZA - - $1,058,353 - - - - $1,058,353
CN TAP Chicago UZA - - $692,947 - - - - $692,947
Total Construction - - $2,189,125 - - - - $2,189,125
Total Programmed $137,500 - $2,189,125 - - - - $2,326,625
Map Coming Soon

Map location not available

<< Go Back
Complete Streets sidewalks on 133rd and Morris (2101110)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2023   CMAQ Chicago UZA   $110,000   $0   $0   $0   $110,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2023   Local Fund   $27,500   $0   $0   $0   $27,500  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   TAP Chicago UZA   $0   $0   $692,947   $0   $692,947  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   STBG Chicago UZA   $0   $0   $1,058,353   $0   $1,058,353  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   Local Fund   $0   $0   $437,825   $0   $437,825  
TOTAL FOR VERSION 3 $137,500   $0   $2,189,125   $0   $2,326,625  
  2   22-03 2022 TIP Amendment January 2022 for 2020-2024 & 2022-2026 TIPs   2023   CMAQ Chicago UZA   $110,000   $0   $0   $0   $110,000  
  2   22-03 2022 TIP Amendment January 2022 for 2020-2024 & 2022-2026 TIPs   2023   Local Fund   $27,500   $0   $0   $0   $27,500  
  2   22-03 2022 TIP Amendment January 2022 for 2020-2024 & 2022-2026 TIPs   2025   TAP Chicago UZA   $0   $0   $692,947   $0   $692,947  
  2   22-03 2022 TIP Amendment January 2022 for 2020-2024 & 2022-2026 TIPs   2025   STBG Chicago UZA   $0   $0   $1,058,353   $0   $1,058,353  
  2   22-03 2022 TIP Amendment January 2022 for 2020-2024 & 2022-2026 TIPs   2025   Local Fund   $0   $0   $437,825   $0   $437,825  
TOTAL FOR VERSION 2 $137,500   $0   $2,189,125   $0   $2,326,625  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   CMAQ Chicago UZA   $110,000   $0   $0   $0   $110,000  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2023   Local Fund   $27,500   $0   $0   $0   $27,500  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   TAP Chicago UZA   $0   $0   $692,947   $0   $692,947  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   STBG Chicago UZA   $0   $0   $1,058,353   $0   $1,058,353  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   Local Fund   $0   $0   $437,825   $0   $437,825  
TOTAL FOR VERSION 1 $137,500   $0   $2,189,125   $0   $2,326,625  
<< Go Back
Complete Streets sidewalks on 133rd and Morris (2101110)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  3     24-00 July 2024-2027 TIP    COMPLETE STREETS SIDEWALKS ON 133RD AND MORRIS   PROGRAMMED     
  2     22-03 January 2022 LOCAL   COMPLETE STREETS SIDEWALKS ON 133RD AND MORRIS   PROGRAMMED   4/20/2022  
  1     22-00 2022-2026 2022 TIP    COMPLETE STREETS SIDEWALKS ON 133RD AND MORRIS   PROGRAMMED   06/17/2022