Summer St Reconstruction (2101127)
Des Number 2101127 Amendment 22-00 STIP Exempt Category Exempt Est Total Project Cost $4,642,229
Contract # Contact (ERC) Dean Button 2198536363 County Lake
Lead Agency Hammond Letting Date 01/19/2023 Functional Classification Minor Collector Bike/Ped Component(s) Yes 05%
Project Type Pavement Reconstruction/Rehabilitation
Title Summer St Reconstruction
Limits
Description The project will reconstruct Summer Street from Willis Street to Indianapolis Boulevard, adding capacity by adding a two-way left-turn lane in the middle of the roadway, while maintaining one lane of travel in each direction. Phase 2
Phase Fund Source Prior SFY SFY2022 SFY2023 SFY2024 SFY2025 SFY2026 Future SFY Total
CN Local Fund - - - - - $928,446 - $928,446
CN STBG Chicago UZA - - - - - $3,713,783 - $3,713,783
Total Construction - - - - - $4,642,229 - $4,642,229
Total Programmed - - - - - $4,642,229 - $4,642,229
Map Coming Soon

Map location not available

<< Go Back
Summer St Reconstruction (2101127)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  2   22-03 2022 TIP Amendment January 2022 for 2020-2024 & 2022-2026 TIPs   2023   Federal Special   $0   $0   $3,470,203   $0   $3,470,203  
  2   22-03 2022 TIP Amendment January 2022 for 2020-2024 & 2022-2026 TIPs   2023   Local Fund   $0   $0   $867,551   $0   $867,551  
TOTAL FOR VERSION 2 $0   $0   $4,337,754   $0   $4,337,754  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2026   STBG Chicago UZA   $0   $0   $3,713,783   $0   $3,713,783  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2026   Local Fund   $0   $0   $928,446   $0   $928,446  
TOTAL FOR VERSION 1 $0   $0   $4,642,229   $0   $4,642,229  
<< Go Back
Summer St Reconstruction (2101127)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  2     22-03 January 2022 LOCAL   SUMMER ST RECONSTRUCTION   PROGRAMMED   4/20/2022  
  1     22-00 2022-2026 2022 TIP    SUMMER ST RECONSTRUCTION   PROGRAMMED   06/17/2022