HGAC
  • Project Overview
  • Funding History
  • Amendment History
<< Go Back
Transit Planning (NIR-25-007)
Des Number NIR-25-007 Amendment 24-00 STIP Exempt Category Exempt Est Total Project Cost $200,000
Contract # Contact (ERC) David Wright 2198857555 County Lake
Lead Agency GPTC Letting Date Functional Classification Not Applicable Bike/Ped Component(s) No
Project Type Transit - Planning/Oversight
Title Transit Planning
Limits
Description Transit Planning for 2025 & 2026 include oversight of GPTC, Civil Rights Review, Outreach and Marketing
Phase Fund Source Prior SFY SFY2024 SFY2025 SFY2026 SFY2027 SFY2028 Future SFY Total
CN FTA 5307 Chicago UZA - - $80,000 $80,000 - - - $160,000
CN Local Fund - - $20,000 $20,000 - - - $40,000
Total Construction - - $100,000 $100,000 - - - $200,000
Total Programmed - - $100,000 $100,000 - - - $200,000
Map Coming Soon

Map location not available

<< Go Back
Transit Planning (NIR-25-007)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  2   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   FTA 5307 Chicago UZA   $0   $0   $80,000   $0   $80,000  
  2   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   Local Fund   $0   $0   $20,000   $0   $20,000  
  2   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2026   FTA 5307 Chicago UZA   $0   $0   $80,000   $0   $80,000  
  2   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2026   Local Fund   $0   $0   $20,000   $0   $20,000  
TOTAL FOR VERSION 2 $0   $0   $200,000   $0   $200,000  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   FTA 5307 Chicago UZA   $0   $0   $80,000   $0   $80,000  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   Local Fund   $0   $0   $20,000   $0   $20,000  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2026   FTA 5307 Chicago UZA   $0   $0   $80,000   $0   $80,000  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2026   Local Fund   $0   $0   $20,000   $0   $20,000  
TOTAL FOR VERSION 1 $0   $0   $200,000   $0   $200,000  
<< Go Back
Transit Planning (NIR-25-007)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  2     24-00 July 2024-2027 TIP    TRANSIT PLANNING   PROGRAMMED     
  1     22-00 2022-2026 2022 TIP    TRANSIT PLANNING   PROGRAMMED   06/17/2022