Substation Improvements (NIR-25-025)
Des Number NIR-25-025 Amendment 24-00 STIP Exempt Category Exempt Est Total Project Cost $12,334,497
Contract # Contact (ERC) Kelly Wenger 2199265744 County Various
Lead Agency NICTD Letting Date Functional Classification Not Applicable Bike/Ped Component(s) No
Project Type Transit - Preventative Maintenance
Title Substation Improvements
Limits
Description This project is to finance the upgrade/replacement program for NICTD's substations in 2025.
Phase Fund Source Prior SFY SFY2024 SFY2025 SFY2026 SFY2027 SFY2028 Future SFY Total
CN FTA 5337 St of Good Repair - - $4,427,598 $5,440,000 - - - $9,867,598
CN Local Fund - - $1,106,899 $1,360,000 - - - $2,466,899
Total Construction - - $5,534,497 $6,800,000 - - - $12,334,497
Total Programmed - - $5,534,497 $6,800,000 - - - $12,334,497
Map Coming Soon

Map location not available

<< Go Back
Substation Improvements (NIR-25-025)
  VERSION   SFY   SOURCE   PE   ROW   CON   CE   TOTAL  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   FTA 5337 St of Good Repair   $0   $0   $4,427,598   $0   $4,427,598  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2025   Local Fund   $0   $0   $1,106,899   $0   $1,106,899  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2026   FTA 5337 St of Good Repair   $0   $0   $5,440,000   $0   $5,440,000  
  3   24-00 2024-2027 NIRPC 2024-2028 TIP Adoption   2026   Local Fund   $0   $0   $1,360,000   $0   $1,360,000  
TOTAL FOR VERSION 3 $0   $0   $12,334,497   $0   $12,334,497  
  2   22-08.5 2023 January 2023 Transit Amendment   2025   FTA 5337 St of Good Repair   $0   $0   $4,427,598   $0   $4,427,598  
  2   22-08.5 2023 January 2023 Transit Amendment   2025   Local Fund   $0   $0   $1,106,899   $0   $1,106,899  
  2   22-08.5 2023 January 2023 Transit Amendment   2026   FTA 5337 St of Good Repair   $0   $0   $5,440,000   $0   $5,440,000  
  2   22-08.5 2023 January 2023 Transit Amendment   2026   Local Fund   $0   $0   $1,360,000   $0   $1,360,000  
TOTAL FOR VERSION 2 $0   $0   $12,334,497   $0   $12,334,497  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   FTA 5337 St of Good Repair   $0   $0   $2,000,000   $0   $2,000,000  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2025   Local Fund   $0   $0   $500,000   $0   $500,000  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2026   FTA 5337 St of Good Repair   $0   $0   $2,000,000   $0   $2,000,000  
  1   22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.   2026   Local Fund   $0   $0   $500,000   $0   $500,000  
TOTAL FOR VERSION 1 $0   $0   $5,000,000   $0   $5,000,000  
<< Go Back
Substation Improvements (NIR-25-025)
  VERSION      PUBLIC DESCRIPTION   STATUS   APPROVAL DATE  
  3     24-00 July 2024-2027 TIP    SUBSTATION IMPROVEMENTS   PROGRAMMED     
  2     22-08.5 January 2023 LOCAL   SUBSTATION IMPROVEMENTS   PROGRAMMED   N/A  
  1     22-00 2022-2026 2022 TIP    SUBSTATION IMPROVEMENTS   PROGRAMMED   06/17/2022