<< Go Back
Facility Improvements (NIR-25-029)
Phase
Fund Source
Prior SFY
SFY2024
SFY2025
SFY2026
SFY2027
SFY2028
Future SFY
Total
CN
FTA 5337 St of Good Repair
-
-
$1,000,000
-
-
-
-
$1,000,000
CN
Local Fund
-
-
$250,000
-
-
-
-
$250,000
Total Construction
-
-
$1,250,000
-
-
-
-
$1,250,000
Total Programmed
-
-
$1,250,000
-
-
-
-
$1,250,000
Map Coming Soon
Map location not available
<< Go Back
Facility Improvements (NIR-25-029)
VERSION
SFY
SOURCE
PE
ROW
CON
CE
TOTAL
2
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2025
FTA 5337 St of Good Repair
$0
$0
$1,000,000
$0
$1,000,000
2
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption
2025
Local Fund
$0
$0
$250,000
$0
$250,000
TOTAL FOR VERSION 2
$0
$0
$1,250,000
$0
$1,250,000
1
22-00 2022 2022-2026 TIP adoption (INDOT originally approved on 7/15/2021, but later recalled approval because USDOT has not approved any TIPs.) Commission approval was granted on 4/15/21. Awaiting State and federal approval.
2025
FTA 5337 St of Good Repair
$0
$0
$1,000,000
$0
$1,000,000
TOTAL FOR VERSION 1
$0
$0
$1,000,000
$0
$1,000,000
<< Go Back
Facility Improvements (NIR-25-029)
VERSION
PUBLIC DESCRIPTION
STATUS
APPROVAL DATE
2
24-00 July 2024-2027 TIP
FACILITY IMPROVEMENTS
PROGRAMMED
1
22-00 2022-2026 2022 TIP
FACILITY IMPROVEMENTS
PROGRAMMED
06/17/2022