|
<< Go Back
|
|
Bridge Thin Deck Overlay (2200750)
|
|
|
|
Phase |
Fund Source
|
Prior SFY |
SFY2024 |
SFY2025 |
SFY2026 |
SFY2027 |
SFY2028 |
Future SFY |
Total |
PE |
NHPP Interstate |
$108,000 |
-
|
-
|
-
|
-
|
-
|
-
|
$108,000 |
Total Preliminary Engineering |
$108,000 |
- |
- |
- |
- |
- |
- |
$108,000 |
CN |
NHPP Interstate |
- |
-
|
-
|
-
|
$610,956
|
-
|
-
|
$610,956 |
Total Construction |
- |
- |
- |
- |
$610,956 |
- |
- |
$610,956 |
Total Programmed |
$108,000 |
-
|
-
|
-
|
$610,956
|
-
|
-
|
$718,956 |
|
Map Coming Soon
Map location not available
|
|
<< Go Back
|
|
Bridge Thin Deck Overlay (2200750)
|
VERSION |
SFY |
SOURCE |
PE |
ROW |
CON |
CE |
TOTAL |
2 |
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption |
2023 |
NHPP Interstate |
$108,000 |
$0 |
$0 |
$0 |
$108,000 |
2 |
24-00 2024-2027 NIRPC 2024-2028 TIP Adoption |
2027 |
NHPP Interstate |
$0 |
$0 |
$610,956 |
$0 |
$610,956 |
|
TOTAL FOR VERSION 2 |
$108,000 |
$0 |
$610,956 |
$0 |
$718,956 |
|
1 |
22-08 2023 January 2023 Amendment |
2023 |
NHPP Interstate |
$108,000 |
$0 |
$0 |
$0 |
$108,000 |
1 |
22-08 2023 January 2023 Amendment |
2027 |
NHPP Interstate |
$0 |
$0 |
$610,956 |
$0 |
$610,956 |
|
TOTAL FOR VERSION 1 |
$108,000 |
$0 |
$610,956 |
$0 |
$718,956 |
|
|
|
|
<< Go Back
|
|
Bridge Thin Deck Overlay (2200750)
|
VERSION |
|
PUBLIC DESCRIPTION |
STATUS |
APPROVAL DATE |
2 |
24-00 July 2024-2027 TIP |
BRIDGE THIN DECK OVERLAY |
PROGRAMMED |
|
1 |
22-08 January 2023 INDOT |
BRIDGE THIN DECK OVERLAY |
PROGRAMMED |
|
|
|
|
|